Search results for "leisure centres"

Including the closely related term leisure centre.

1 result

East Hertfordshire District Council

Direct link to action plan (XLSX)

… Assessment and hydraulic designs for new planning application Continuing to develop information for full submission NO £26,622 Jonathan Geall £211,000 Hartham Leisure Centre Emily Coulter Planning permission deferred at DMC in January Review period being undertaken Planning deferred due to issues with design / massing and sustainability NO £620,997 Jess Khanom S257 application to be applied…

… for during review period £8,746,000 Risk assessment of Hartham roof to be undertaken during review Plus £950,000 (sustainability) Grange Paddocks Emily Coulter Planning permission granted in November. Contract for RIBA stages 4-7 agreed and technical design commences. Construction risks for the leisure centre will be outlined to key services in an Executive summary of the delivery agreement…

…. A contingency allowance has been retained. NO £1,613,861 £23,221,939 Jess Khanom EA permit achieved for temporary bridge. Start of construction phase 3G pitch site continues to be explored through consulting the EA and understanding trees on the site. Geo-tech surveys to be considered for the site. Plus £50,000 (sustainability) Final cost agreed for leisure centre construction contract, with contracts…

… to recent climate agenda Development Control have revised their guidance as part of the Grange Paddocks Leisure Centre build project to require the courts to be located further north in the old town tip area but grouped together with the proposed 3G football pitch.  This has created some difficulty in fitting both improvements into the space without compromising a nearby drainage channel and adjacent…

… trees.  Solutions currently being explored by leisure centre consultants. Expansion of community events programme First phase of tree works completed. Considering change to air source heat pumps Project Management Consultancy Contract agreed by NLHF and awarded. Contract to design conservation works to restore Castle Remains awarded Design Interpretation Contract awarded to create signage…