Including 7 closely related terms such as energy consumption, energy performance, and energy performance.
… buildings Action Service Resources Milestone 1 Milestone 2 Milestone 3 Completion date Target 1.2 Bid for future central government funding and other green energy funding available for investments in energy efficiency and decarbonisation measures in the Council’s corporate buildings Various Council Services Corporate Energy Manager Identify and prepare…
… and communicated to staff - August 2021 - - August 2021 - OBJECTIVE 2: Reducing energy consumption and carbon emissions from homes and buildings in Cambridge Action Service Resources Milestone 1 Milestone 2 Milestone 3 Completion date Target 2.1 Investing £2.5 million in energy efficiency improvements to Council homes with poor energy efficiency ratings…
… (predominantly Energy Performance Certificate D to G rated stock) from 2020/21 to 2021/22. Estates and Facilities Energy Assessor/ surveyor role and part of Corporate Energy Manager time August 2021 Phase 1 of works completed. March 2022 completion of project - March 2022 To reach a minimum of EPC C (B where possible) in at least 140 Council…
… Deliver energy efficiency and renewable energy projects identified in the Council’s Carbon Management Plan for 2021-2026 to reduce carbon emissions from corporate buildings (including swimming pools, sheltered and temporary housing, administrative buildings, car parks, community centres, the Corn Exchange and the crematorium). Estates and Facilities, Corporate…
…; Facilities Complete assessment of all Energy Performance Certificates for commercial properties - August 2021 Action plans for all properties to be prepared to identify prioritisation and asset management decisions for costed programme through to 2030 - Budget bids to be prepared for 2023/24 onwards for any costs not within existing allocated…