Basingstoke and Deane Borough Council

Direct link to action plan (PDF)

… to continue to add and develop actions throughout delivery against the high-level aspirations set out in the strategy. Areas of focus for the Action Plan: Our approach to tackling the Climate Emergency commitments, both for our council operations and borough-wide emissions, will be focused in 6 main categories: • Action by all – the need for everyone in the borough to contribute • Buildings

… to cost and explore powering leisure facilities using renewable energy High 300 tCO2e for electricity TBC Q1 2021 – 2023 Agreement reached Measured CO2 reduction 2.3 Ensure office and council operational buildings are used as efficiently as possible, and fit for the future as we work more flexibly Medium Estimated at c. 180tCO2e TBC Q2 2021 Office energy consumption…

… Office occupancy 2.4 Undertake review of possible energy efficiency and reduction measures on council campus Enabler TBC TBC Audit undertaken 2.5 Undertake audit of other council operational buildings to determine options to reduce energy consumption Enabler TBC 2021 Audit undertaken 2.7 Install LED lighting in Eastlands council car park (as demo project for wider rollout…

…) Medium c. 28.5 tCO2e per year £100k By Q2 2021 Reduced electricity consumption and CO2 2.8 Work with development partners to ensure new council building development to be as energy efficient as a possible High High Ongoing Energy efficiency ratings of new developments 2.9 To include climate change mitigation and adaptation as a central theme within the Local Plan Update, being…

… High 700 tCO2e Low uplift Complete CO2 reduction in annual reporting 4.2 Review suitability of council buildings/land for installation of renewable electricity generation High Minimal cost to review – projects would need to be scoped subsequently By mid 2021 No. of sites identified Installed renewable capacity 4.3 Engage with strategic infrastructure providers National Grid…