Emissions reduction projects

Local authorities in Scotland are required to publish yearly data on their compliance with their climate change duties – including the emissions reduction projects they are undertaking.

54 projects

Perth and Kinross Council

BMS Upgrade Blair Atholl Primary (2017)

Lifespan
30 years
Emission source
Gas Oil
Emissions saved
4 tCO2e per year
Capital cost
£7,000
Annual savings
£750
Perth and Kinross Council

Relocation of Control Sensor, Perth High (2017)

Lifespan
30 years
Emission source
Natural Gas
Emissions saved
4 tCO2e per year
Capital cost
£1,000
Annual savings
£450
Perth and Kinross Council

BMS Upgrade Our Laddies Primary (2017)

Emission source
Natural Gas
Emissions saved
2 tCO2e per year
Capital cost
£6,000
Annual savings
£220
Perth and Kinross Council

Madderty Primary - roof insulation & Cavity wall insulation (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
2.5 tCO2e per year
Capital cost
£8,000
Annual savings
£1,000
Perth and Kinross Council

6 no. Community Campus Lighting controls installations (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
10 tCO2e per year
Capital cost
£20,000
Annual savings
£3,500
Perth and Kinross Council

Tulloch & Kinross – SCAN software in use analysis (2018)

Funding source
Energy Conservation
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
4 tCO2e per year
Capital cost
£11,000
Annual savings
£1,000
Perth and Kinross Council

Kinloch Rannoch Primary – Roof Insulation & Cavity wall insulation (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
3 tCO2e per year
Capital cost
£11,000
Annual savings
£1,300
Perth and Kinross Council

Viewlands Primary – HW Cylinder replacement (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Natural Gas
Emissions saved
22 tCO2e per year
Capital cost
£13,000
Annual savings
£2,400
Perth and Kinross Council

Perth Academy – HW Cylinder replacement (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Natural Gas
Emissions saved
22 tCO2e per year
Capital cost
£13,000
Annual savings
£2,400
Perth and Kinross Council

Auchterarder Library – Lighting and Lighting Controls Upgrade (2018)

Funding source
CEEF
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
4 tCO2e per year
Capital cost
£19,000
Annual savings
£1,800
Perth and Kinross Council

Dunbarney PS – BMS upgrade (2018)

Funding source
Energy Conservation
Lifespan
25 years
Emission source
Natural Gas
Emissions saved
9 tCO2e per year
Capital cost
£24,000
Annual savings
£1,000
Perth and Kinross Council

Perth Crematorium – PV install (2018)

Funding source
Prudential Borrowing
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
2 tCO2e per year
Capital cost
£39,000
Annual savings
£500
Perth and Kinross Council

Auchterarder Gymnasium and changing room LED refurb and lighting controls (2018)

Funding source
CEEF
Lifespan
25 years
Emission source
Grid Electricity
Emissions saved
6.9 tCO2e per year
Capital cost
£67,000
Annual savings
£2,840
Perth and Kinross Council

BMS Upgrade - 80 SITEs (2020)

Funding source
Capital/prudential borrowing
Lifespan
15 years
Emission source
Natural Gas
Emissions saved
175 tCO2e per year
Capital cost
£300,000
Annual savings
£50,000